Skip to content

Borehole Rehabilitation – Umuahia Central

  • by

Rehabilitation of 10 Boreholes and Installation of 2 new Boreholes in Umuahia Central Constituency. This project kicked off Jan 1, 2025 and was completed April 30, 2025.

Water Supply – Okwoyi

Integrated Solar Water Projects at Okwoyi. The project kicked off 28th Jan 2025 and was completed 3rd May 2025

Rural Electrification – Arochukwu

Supply and Installation of 500KVA/33KV Transformer Substation at Abia State College of Education Technical Arochukwu. This project kicked off  21st Jan, 2025 and was completed 4th March,, 2025.

Power Extension

Installation of 500KVA/33KV Transformer at Abia State Teaching Hospital Abayi Aba. This project kicked off 10th April 2025 and  was completed 16th May 2025.